Zenitaka Major Works

Quarrying Work for Moriyoshizan Dam
Civil EngineeringTohokuDam/Regulating Reservoir2006~2010


| Owner | Tohoku Regional Development Bureau, Ministry of Land, Infrastructure, Transport and Tourism |
|---|---|
| Location | Moriyoshi, Kita-akita City, Akita Prefecture |
| Completion | October, 2008 |
| Work Summary | Quarrying Work for Rock-fill Dam Surface soil and waste rock processing work: 1,744,100m3 Stone extraction work 1,923,200m3 Material extraction work 142,400m3 Aggregate manufacturing work 211,170t Explosives 1,273t Slope protection work 26,260㎡ Miscellaneous work |